Richardson Street Roadway & Storm Drain Improvements

  • Project typePublic Works
  • Project scheduleWork must begin no later than June 1, 2026. The intent is for the work to reach substantial completion by July 2, 2027, and final completion no later than August 2, 2027.
  • Bids DueApril 02, 2026

The City of Bath is seeking bids for stormwater infrastructure improvements including storm drain replacement and pavement repairs on State Road, Pine Hill Drive, West Street, and Richardson Street. Work includes catch basin disconnections from sewer, new cross-country storm drain to Western Avenue, and reconstruction of the Lilac and Richardson intersection.

A non-mandatory pre-bid conference for the Project will be held on Thursday, March 12, 2026, at 2:00 PM at Bath City Hall, 55 Front Street, Bath, ME 04530. Bidders must submit their proposals by April 2, 2026 at 2:00 PM

 

 

Location

Richardson Street,  04530  View Map