Fire Station Project

On November 8, 2022, voters approved a $13.05 million bond referendum for the design, construction, and equipping of a new fire station. The project will replace the current fire station at 864 High Street and will be located at the north end of the former Morse High School property on High Street.The current fire station, which opened in 1958, was prioritized for replacement due to the level of deficiencies, the needs of the department, and the location of the site.

 

 

Project Timeline

Design: June 2024-Fall 2025
Construction: Spring 2026-Fall 2027

Current Status: The project completed the bid opening for the construction of the new building on Tuesday, November 4, 2025. 

2021

October 29, 2021 - Fire Station Residential Analysis

May 7, 2021 - Morse High School Reuse Study

 

2022

November 8, 2022 - Bond Referendum Results

October 27, 2022 - Public Informational Meeting

October 21, 2022 - Fire Station Tour

  • Station Tour Video

August 3, 2022 - City Council Approval of Bond Referendum

July 22, 2022 - Concept Drawings and Probable Cost Estimates

June 15, 2022 - City Council Fire Station Workshop

 

2025

  • Cost Estimating: Two independent cost estimates were completed and are being reconciled to ensure the project remains within budget.
  • Permitting: The Maine DEP permit application has been submitted.
  • Alerting System: Design for the Fire Station Alerting System is underway and will continue through May 2025
  • Design & Engineering: The project has entered the Construction Documents phase, with drawings and specifications being finalized throughout May and June.
  • Utility Coordination: The team is awaiting a cost estimate from Central Maine Power to raise overhead power lines.
  • Site Plan: The project received site plan approval from the Planning Board at their May meeting.